MILTON KEYNES
S278 Works
Value of works:
£650k
Scope Of Works:
- Site clearance including removal of 1000m2 of existing footpath, kerbs and edging and removal off site
- Installation of 1250m of PCC kerbs
- Removal of street light columns and replace
- Signage and white lining package
- Re-surfacing of carriageway and new footpaths
- Gripple retaining system to bank works including cut & fill in layers as per design
- Swale works with headwall
- Replacing manhole and gully ironworks